Tender for Civil Engineering Construction Projects Related to the Adjustment of the Snow Removal Vehicle Production Line
Release Date:
2025-04-06
Chapter One Invitation to Bid
Company:
Our company is concerned with Adjustment of Civil Engineering Construction for the Snow Removal Vehicle Production Line Project A tender is being conducted, and your organization is hereby cordially invited to submit a bid. Should you accept the invitation to participate in the bidding, please follow the procedures and formalities set out below:
- Tender Number: CGZXCX-202504-3940
- Project Name: Civil Engineering Construction Project for Adjusting the Snow Removal Vehicle Production Line
- Bidders participating in the tender must carefully read the Instructions to Bidders and all other provisions in the Tender Documents to avoid any errors.
- Bids must be submitted in writing no later than 4:00 p.m. on April 16, 2025, together with a bid bond of RMB 5,000. Late submissions will not be accepted. The bid bonds of unsuccessful bidders will be refunded within 20 working days after the announcement of the tender results; the bid bond of the successful bidder will be converted into a performance bond. The submission address for bid documents is the Manufacturing Department of China National Heavy Duty Truck Group Liuzhou Yunli Special-Purpose Vehicle Co., Ltd.
- The bid opening is tentatively scheduled for 2:00 p.m. on April 17, 2025, in the Conference Room of the Manufacturing Department of China National Heavy Duty Truck Group Liuzhou Yunli Special-Purpose Vehicle Co., Ltd., and will be conducted as an open tender.
- Contact and inquiry phone number and mailing address:
Unit: China National Heavy Duty Truck Group Liuzhou Yunli Special-Purpose Vehicle Co., Ltd.
Address: No. 12, Leye Road, Xinxing Industrial Park, Liuzhou City
Postal Code: 545112
Phone: 13877223810
Fax: 0772-3269378
Email: 691896511wang@163.com
Account Name: China National Heavy Duty Truck Group Liuzhou Yunli Special-Purpose Vehicle Co., Ltd.
Account-opening Bank: Liujiang Xinxing Sub-branch of Agricultural Bank of China Co., Ltd.
Account Number: 2013 2401 0400 0157 1
Contact: Wang Le
China National Heavy Duty Truck Group Liuzhou Yunli Special-Purpose Vehicle Co., Ltd.
2025 April 6th, Year
Chapter 2 Instructions for Bidding
1 1. Preliminary Schedule of Instructions to Bidders
|
Project |
Content |
Instructions and Requirements |
|
1 |
Definition |
Tendering Entity: China National Heavy Duty Truck Group Liuzhou Yunli Special-Purpose Vehicle Co., Ltd. |
|
2 |
Bidding Content (Detailed in Chapter 8) |
Project Renovation Scope |
|
3 |
Quality Standards |
Ultimately, acceptance shall be conducted by the tendering party in accordance with national or industry standards. |
|
4 |
Qualification Review |
Subject to approval by the tendering party |
|
5 |
Quotation method (tax-inclusive price) |
Provide detailed quotations for each item in accordance with the tender specifications. |
|
6 |
Tender Validity Period |
Before the deadline for submission of tender documents |
|
7 |
Guarantee |
Upon winning the bid, the bid bond shall be converted into a performance bond. |
|
8 |
Collect the tender documents |
Receive via paper document or electronic file |
|
9 |
On-site inspection |
2025 year 4 month 12 Morning 10:00 A site inspection will be conducted, with all bidders accompanied by personnel dispatched by the tendering party. The location is the east side of the Phase III factory building of China National Heavy Duty Truck Group Liuzhou Yunli Special-Purpose Vehicle Co., Ltd. |
|
10 |
Deadline for Submission of Bidding Documents |
2025 Deadline: 4:00 PM on April 16 |
|
11 |
Will the tender documents be returned? |
Non-refundable |
|
12 |
Bid Opening Time |
2024 April 17 at 2:00 PM |
|
13 |
Evaluation Committee Members |
Tendering Party |
|
14 |
Bidding opening method |
Sealed and Unordered Bid Opening |
|
15 |
Project Schedule Requirements |
10 calendar day |
2 1. Bidding Instructions条款
2.1 Party A: The Tendering Party (China National Heavy Duty Truck Group Liuzhou Yunli Special-Purpose Vehicle Co., Ltd.)
Party B: Bidder
2.2 The bidder shall submit the relevant qualification documents, including qualification certificates, a copy of the business license, the organization code certificate, equipment manufacturing and installation certificates, proof of the legal representative, a power of attorney, and photocopies of the identification cards of both the legal representative and the authorized representative.
2.4 The subject of this tender is the civil engineering construction project for the adjustment of the snow removal vehicle production line.
2.5 Bidding Price: A detailed quotation shall be provided in accordance with the schedules in Chapter 9 (prices are quoted inclusive of tax).
3 , Expense Settlement
3.1 Payment Method: Party A shall make the corresponding payment by way of a six-month electronic acceptance bill.
3.2 Upon successful completion and acceptance of the project, Party B shall, in accordance with the agreed settlement cycle, submit complete settlement documentation to a third-party auditing firm approved by both parties for audit (with audit fees borne by the contractor), and settlement shall be conducted based on the audited amounts. Party B shall also provide a special value-added tax invoice that is consistent with the settled amount and complies with national requirements; upon verification by Party A in accordance with its financial regulations and confirmation of accuracy, 30 Pay the audited and settled project amount within one working day. 95% , the audit settlement amount for the remaining works 5% As a quality guarantee deposit, The quality guarantee deposit shall bear no interest during the warranty period, and any defects discovered in the works during such period shall result in a corresponding deduction from the deposit.
4 , Performance Bond
To ensure the performance of this Agreement, Party B’s bid bond shall be converted into a performance bond. If Party B unilaterally terminates the Contract midway, Party A shall not refund Party B’s performance bond. Upon successful acceptance in accordance with the Contract requirements, Party A shall refund Party B’s performance bond within 20 working days.
5 , Quality Control
Party B shall, in accordance with the scope of work awarded under the bid, ultimately obtain acceptance by Party A in compliance with national or industry standards.
5.1 For the installation of equipment that is subject to inspection by the state or relevant industry authorities, Party B shall handle the requisite procedures in accordance with such inspection requirements and ensure that the equipment passes the acceptance inspection.
5.2 The warranty period for construction works and equipment installation is one year.
6 , Liability Protection
6.1 Party A’s Responsibilities:
(1) Provide the site required for construction and the materials specified in the documents.
(2) Upon fulfillment of the construction conditions, Party B shall be notified two days in advance to commence construction.
6.2 Party B’s Responsibilities:
(1) Party B shall be responsible for organizing construction in accordance with the scope of the winning bid and the schedule specified by Party A, and the work must ultimately pass Party A’s acceptance inspection.
(2) With respect to equipment that is subject to inspection by the state or relevant industry authorities, if the performance of the equipment as specified in Party B’s documentation or upon completion of installation fails to meet the requirements stipulated by such inspections, Party B shall be liable for breach of contract, and shall bear full responsibility for any economic losses incurred by Party A as a result.
6.3 Upon entering Party A’s premises, Party B’s personnel shall comply with Party A’s relevant management regulations, bring and use qualified safety equipment and personal protective equipment, ensure safe and civilized construction practices, and adhere to applicable occupational safety and health regulations. Any occupational safety accidents occurring during the course of construction, or any personal injury or property damage caused to third parties, shall be the sole responsibility of Party B.
Chapter 3 Bid Opening
Party A shall conduct the bid opening at the prescribed time and in the designated venue, and shall invite the legal representative (or head of the entity) of each Party B, or their duly authorized agent, to attend on time. Personnel representing the bidders at the bid-opening meeting shall be thoroughly familiar with the key performance indicators and technical features of the equipment being tendered, so as to provide responses and clarifications during the evaluation process. Failure by a bidder to attend the bid-opening shall be deemed as acceptance of the bid-opening results.
Chapter Four Bid Evaluation
1 1. Party A shall organize relevant professionals to conduct the bid evaluation, which shall be carried out through multiple rounds of bidding and a tiered elimination process. Determine the winning bidder, No explanations will be provided to unsuccessful bidders. 。
2 1. If a tender document falls under any of the following circumstances, the Evaluation Committee shall treat it as non-responsive to the tender documents or as an invalid bid:
1 ) The sample does not comply with the requirements stipulated in the tender documents;
2 ) Where the tender document is not stamped by the bidder, or where it is not signed or stamped by the legal representative or by an authorized agent duly authorized by the legal representative;
3 ) Not sealed or completed in accordance with the prescribed format, with incomplete content or illegible key information that cannot be identified;
4 ) Where a bidder submits two or more quotation documents with differing contents, or includes two or more quotations for the same procurement item in a single quotation document without specifying which one is valid, except where alternative proposals are submitted in accordance with the provisions of the tender documents;
5 ) The bidder’s name or organizational structure is inconsistent with the qualification review;
6 ) The bidder fails to provide the bid bond as required by the tender documents;
7 ) Where the content of tender documents submitted by different bidders is abnormally consistent;
8 ) Where the tender documents of different bidders are intermingled;
9 ) Where different bidders entrust the same person to submit bids;
10 ) Where different bidders use the same individual’s or enterprise’s funds to pay the bid bond;
11 ) Failing to comply with the substantive requirements in the tender documents regarding delivery schedules, quality standards, warranty periods, and other such matters;
12) Providing false materials to obtain the bid;
13 ) Any other activities intended to compromise the fairness of the tender outcome.
Chapter 5 Contract Terms
Contract Execution: The contract shall be executed within 2 days of receipt of the notice of award.
Chapter 6: On-Site Investigation
The tendering party will uniformly organize a site inspection for all bidders at 14:00 on April 12, at the construction site.
Chapter 7 Preparation of Bidding Documents
1、 The bidder’s tender document consists of three parts: qualification certification documents, the technical section of the tender document, and the commercial section of the tender document. 。
1.1 Qualification Certification Documents
1 ) Copy of business license;
2 ) Power of Attorney;
3 ) Photocopies of the legal person’s and the authorized representative’s identification cards;
4 ) A copy of the bank transfer slip for the bid bond.
2 , Technical Section
2.1 Construction Organization (Please indicate whether on-site personnel are stationed)
1 ) Measures to ensure construction efficiency;
2 ) Technical organizational measures to ensure the quality of construction works;
3 ) Technical and organizational measures to ensure safe production;
4 ) Technical and organizational measures to ensure civilized construction;
2.2 Project Management Organization: The project team is fully staffed, with robust technical expertise across all disciplines.
2.3 Corporate Reputation and Strength: Recent three-year track record of similar projects.
3 , Business Section
3.1 Letter of Bid;
3.2 Bidding Price Summary Table;
3.3 Bidder’s Undertaking
Note: For forms provided in the tender documents, fill them out in the prescribed format; for those not specified, bidders shall prepare their own forms, provided that they include the aforementioned contents. ; The above three sections shall be bound into a single bidding document.
Chapter 8: Project Renovation Scope
8.1 Project Technical Requirements:
- Constructing and commissioning a carport
1.1 Commissioning the hardening of the carport floor, with a hardened area of 280 ㎡, use C30 Concrete pouring 20cm Thick;
1.2 Commissioning the carport construction; the carport is to be built at the same height as the south-facing profile storage building, with a roof made of 5.0 Thick single-layer color steel roofing, area 260 ㎡, column 8 Root, adopt 220 Hot-dip galvanized round pipe;
1.3 Adjust the perimeter of the carport; the east and north sides of the carport shall use 5.0 Thick single-layer color steel roofing around the perimeter, with transparent roofing panels used for spacing to ensure adequate daylighting; perimeter area 310 square meters.
2 The canopy at the northeast corner of the Phase III workshop encloses a warehouse.
2.1 The footprint of the warehouse enclosed by the canopy 42 ㎡, columns are used 120*120*2.5 Thick hot-dip galvanized square tube, tiles used 5.0 Thick single-layer color steel roofing;
2.2 The perimeter area of the warehouse enclosed by the canopy 138 ㎡, tiles used 5.0 Thick single-layer color steel roofing.
3 1. Renovation of the hydraulic commissioning shed in the Phase III workshop
3.1 Remove the rolling shutters of the Phase III hydraulic commissioning prefabricated building;
3.2 Open a tall window on the south side of the hydraulic commissioning control room. 2m , wide 1.2m the door;
3.3 Install a door at the location where the rolling shutter is removed. 12mm Thick 2m *4m Transparent tempered glass, with tempered glass used on the top and bottom edges. 5cm Edge sealing with thick rock wool boards.
4 , Add 1 Temporary Debugging Cabin
4.1 The land area of the newly added prefabricated buildings is 7m * 7.5m = 52.5 ㎡, the total perimeter area is 86 square meter ;
4.2 Add a tall window to the prefab building. 2m , wide 1.2m the door;
4.3 Add one door to the prefab building. 12mm Thick 2m*5m Transparent tempered glass, with tempered glass used on the top and bottom edges. 5cm Edge sealing with thick rock wool boards.
8.2 The recommended list of major material brands is as follows:
|
Serial Number |
Material Name |
Brand |
Requirements |
|
1 |
Electrical wire |
Guilin International |
|
|
2 |
Color steel roofing tiles |
None |
Samples are required. |
|
3 |
Cement |
Yufeng, a brand under China Resources Group |
|
Chapter 9 Appendices
Explanation:
1 1. Bidders must carefully complete and submit the attached documents in this section;
2 1. Clear responses shall be provided to the requirements set forth in the attached document;
3 The signatory of the attached documents shall warrant that all responses to inquiries, all statements made, and all qualification and credential documents and materials submitted are true and accurate.
4 The tendering entity shall maintain the confidentiality of the documents and materials submitted by bidders; however, such materials will not be returned.
5 1. All attached documents shall be written in Chinese and shall form part of the bidding documents.
Attachment 1:
Bid Opening Summary Table
|
Bidder Name |
|
|
|
Project Name |
|
|
|
Total Bid Price |
Uppercase: |
|
|
Lowercase: |
||
|
Project delivery date |
From the date of receipt of the Notice of Award, Complete project maintenance and commissioning within one calendar day and deliver it for use. |
|
|
Warranty period |
From the date of signature of the Final Acceptance Report (whichever date is later) year. |
|
Note: The total bid price must match the total quoted amount shown in the detailed bid quotation schedule.
Bidder’s Name (Seal)
Signature of the legal representative or authorized agent:
day Period:
Appendix II:
Quotation List for Civil Engineering Construction Project Adjustments to the Snow Removal Vehicle Production Line
Project Name: Tender Number:
|
Subcontract Number Serial Number |
Project |
Unit |
Quantity |
Unit Price (RMB) |
Total Price (RMB) |
Brand/Specification Model |
|
1 |
|
|
|
|
|
|
|
2 |
|
|
|
|
|
|
|
3 |
|
|
|
|
|
|
|
4 |
|
|
|
|
|
|
|
5 |
|
|
|
|
|
|
|
6 |
|
|
|
|
|
|
|
7 |
|
|
|
|
|
|
|
8 |
|
|
|
|
|
|
|
9 |
|
|
|
|
|
|
|
10 |
|
|
|
|
|
|
|
11 |
|
|
|
|
|
|
|
12 |
|
|
|
|
|
|
|
13 |
|
|
|
|
|
|
|
14 |
|
|
|
|
|
|
|
15 |
|
|
|
|
|
|
|
16 |
|
|
|
|
|
|
|
17 |
|
|
|
|
|
|
|
18 |
|
|
|
|
|
|
Official Account
Quick Navigation
Service Hotline:0772-3269371
Sales Hotline:0772-3269368
Business Inquiry:18507729998(Manager Zhang)
Address: No. 12, Leye Road, Xinxing Industrial Park, Liujiang District, Liuzhou City
Copyright © 2026 SINOTRUK Liuzhou Yunli Special Vehicle Co., LTD.